At a glance
- The application covers the Macquarie Engineering and Technology Campus at 2 Alma Road in the city of Ryde.
- The budget implies roughly AU$10 million per megawatt, a benchmark for allocators underwriting Sydney data center capacity.
- Macquarie said in July 2025 it aimed to develop 150MW of new Sydney capacity, a figure the Alma Road filing exceeds at a single campus.
Macquarie Data Centres has filed a SEARS application with the New South Wales government for a 200MW campus in Sydney's Macquarie Park, budgeted at AU$2 billion (US$1.35 billion), Data Center Dynamics reported.
The application covers the Macquarie Engineering and Technology Campus at 2 Alma Road in the city of Ryde. The 42,015 sqm (452,245 sq ft) development would replace two office buildings on a 3.4-hectare site and could run to six stories. Development timelines were not shared.
The budget implies roughly AU$10 million per megawatt, a benchmark for allocators underwriting Sydney data center capacity. Macquarie's existing and in-development Macquarie Park buildings total 65MW across 30,000 sqm, so the Alma Road filing alone is about three times that campus capacity.
Macquarie said in July 2025 it aimed to develop 150MW of new Sydney capacity, a figure the Alma Road filing exceeds at a single campus. The application enters the same New South Wales planning queue that Goodman Group left in September, when it withdrew a 90MW Sydney data center application citing a policy shift, as Private Wealth Daily previously reported.
Alma Road would be three times Macquarie Park's capacity
Data center capacity in MW: proposed, targeted, existing and withdrawn Sydney projects
- Alma Road campus (proposed)200 MW
- 150MW Sydney target (Jul 2025)150 MW
- Goodman Sydney filing (withdrawn)90 MW
- Macquarie Park existing total65 MW
Show as table
| Item | Value (MW) |
|---|---|
| Alma Road campus (proposed) | 200 MW |
| 150MW Sydney target (Jul 2025) | 150 MW |
| Goodman Sydney filing (withdrawn) | 90 MW |
| Macquarie Park existing total | 65 MW |
Reported by the Data centers & fiber desk from Data Center Dynamics and Private Wealth Daily archive. Published . Corrections