Macquarie Data Centres files for 200MW Sydney campus

The Macquarie Park plan covers 42,015 sqm and would replace two office buildings on a 3.4-hectare site.

$2BBudgeted spend on the 200MW Macquarie Park campus

At a glance

  1. The application covers the Macquarie Engineering and Technology Campus at 2 Alma Road in the city of Ryde.
  2. The budget implies roughly AU$10 million per megawatt, a benchmark for allocators underwriting Sydney data center capacity.
  3. Macquarie said in July 2025 it aimed to develop 150MW of new Sydney capacity, a figure the Alma Road filing exceeds at a single campus.

Macquarie Data Centres has filed a SEARS application with the New South Wales government for a 200MW campus in Sydney's Macquarie Park, budgeted at AU$2 billion (US$1.35 billion), Data Center Dynamics reported.

The application covers the Macquarie Engineering and Technology Campus at 2 Alma Road in the city of Ryde. The 42,015 sqm (452,245 sq ft) development would replace two office buildings on a 3.4-hectare site and could run to six stories. Development timelines were not shared.

The budget implies roughly AU$10 million per megawatt, a benchmark for allocators underwriting Sydney data center capacity. Macquarie's existing and in-development Macquarie Park buildings total 65MW across 30,000 sqm, so the Alma Road filing alone is about three times that campus capacity.

Macquarie said in July 2025 it aimed to develop 150MW of new Sydney capacity, a figure the Alma Road filing exceeds at a single campus. The application enters the same New South Wales planning queue that Goodman Group left in September, when it withdrew a 90MW Sydney data center application citing a policy shift, as Private Wealth Daily previously reported.

Alma Road would be three times Macquarie Park's capacity

Data center capacity in MW: proposed, targeted, existing and withdrawn Sydney projects

  • Alma Road campus (proposed)200 MW
  • 150MW Sydney target (Jul 2025)150 MW
  • Goodman Sydney filing (withdrawn)90 MW
  • Macquarie Park existing total65 MW
Source: Data Center Dynamics; Private Wealth Daily archive
Show as table
ItemValue (MW)
Alma Road campus (proposed)200 MW
150MW Sydney target (Jul 2025)150 MW
Goodman Sydney filing (withdrawn)90 MW
Macquarie Park existing total65 MW

Reported by the Data centers & fiber desk from Data Center Dynamics and Private Wealth Daily archive. Published . Corrections

Related

Infrastructure

Goodman withdraws 90MW Sydney data center application, citing policy shift

The AU$1.2 billion Lane Cove campus, in planning since March 2025, leaves the New South Wales queue while four other Sydney sites stay in development.

Infrastructure

AirTrunk and Stockland cancel Sydney data center plans

Quantum DC's Tungkillo project is paused, and AirTrunk called its Lane Cove West site unsuitable.

Infrastructure

Digital Realty and Goodman bid for NextDC stake at 45.5% premium

The AU$9.50-a-share offer for a 9.9% stake follows NextDC's pause on development during a delayed Melbourne power upgrade.

Infrastructure

Orennia estimates 191 GW of planned data center capacity at risk

Exposure after the midterms concentrates in Texas, Ohio and Georgia, where incoming Democratic governors campaigned on restricting construction.

Infrastructure

Optimum skips $102.5m in interest payments on $22bn debt

CSC Holdings has until around Dec. 16 before the missed payment counts as a default, and a steering committee of debtholders is negotiating a restructuring.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections