At a glance
- The joint venture will support Revera's 1 GW storage portfolio.
- The two projects are the 200 MW Windyhill BESS in Bearsden and the 400 MW Hunterston BESS in North Ayrshire.
- Allocators assessing the deal have a 600 MW construction-stage benchmark, with construction risk to weigh before Windyhill begins operations in the fourth quarter of 2027.
Macquarie Capital will invest alongside Carlyle-backed Revera Energy in two Scottish battery projects totaling 600 MW, the firms said Nov. 18. The joint venture will support Revera's 1 GW storage portfolio. Terms were not disclosed.
The two projects are the 200 MW Windyhill BESS in Bearsden and the 400 MW Hunterston BESS in North Ayrshire. Windyhill reached financial close in February 2026 and is expected to begin commercial operations in the fourth quarter of 2027. Hunterston reached financial close in September 2026, with commercial operations expected in the third quarter of 2028. Both projects are transmission-connected and remain under construction.
Allocators assessing the deal have a 600 MW construction-stage benchmark, with construction risk to weigh before Windyhill begins operations in the fourth quarter of 2027. Macquarie Capital is investing from its infrastructure principal unit, led by David Roseman.
Revera will continue to oversee construction, commercialization and long-term asset management, while Macquarie Capital provides strategic guidance and takes part in governance. The firms said the venture may be extended to other UK assets, including the 400 MW Kincardine BESS.
David Roseman, global head of Macquarie Capital Infrastructure Principal, said Windyhill and Hunterston stood out for their development quality and strategic locations within the UK grid. Carlyle launched London-based Revera last year, and the developer builds, owns and operates battery storage, renewable energy and green hydrogen projects in the UK and Australia. Revera said the agreement will let it recycle capital into additional projects in both markets.
Windyhill delivers first, Hunterston in 2028
Financial close and expected commercial operations dates, two Scottish battery projects
- Feb 2026Windyhill BESS (200 MW) reaches financial close (Completed)
- Sep 2026Hunterston BESS (400 MW) reaches financial close (Completed)
- Q4 2027Windyhill expected to begin commercial operations (Upcoming)
- Q3 2028Hunterston expected to begin commercial operations (Upcoming)
Show as table
| Date | Event | Detail |
|---|---|---|
| Feb 2026 | Windyhill BESS (200 MW) reaches financial close | |
| Sep 2026 | Hunterston BESS (400 MW) reaches financial close | |
| Q4 2027 | Windyhill expected to begin commercial operations | |
| Q3 2028 | Hunterston expected to begin commercial operations |
Reported by the Transition Finance desk from ESG Today. Published . Corrections