Skip to content
Tuesday, November 17, 2026 · Today’s edition, 6:30 a.m. ETTue, Nov 17 · 6:30 a.m. editionSign inMy Desk 0EditionsSign in

LS Power to buy 4.9 GW of gas capacity from NRG for $4B

Proceeds fund a $1 billion buyback and $2 billion of debt repayment, with closing expected in the second quarter of 2027.

At a glance

  1. LS Power approached NRG with an unsolicited offer.
  2. Gaudette said the price is roughly eight times the portfolio's $500 million in annual adjusted EBITDA.
  3. Funds holding merchant gas in ERCOT can use the sale's two valuation marks to test carrying values.

NRG Energy agreed to sell about 4.9 GW of gas-fired capacity to LS Power for $4 billion, CEO Robert Gaudette said on the company's Nov. 9 earnings call. LS Power approached NRG with an unsolicited offer.

Gaudette said the price is roughly eight times the portfolio's $500 million in annual adjusted EBITDA. Utility Dive reported the transaction on Nov. 16. NRG plans to direct $1 billion to a stock buyback, $2 billion to debt reduction, and the remaining $1 billion to what Gaudette called "flexibility to reinvest in our long-term strategy through attractive contracted growth opportunities or further reduce debt."

Funds holding merchant gas in ERCOT can use the sale's two valuation marks to test carrying values. At the plant level, Gaudette put Jack County, a 1.2-GW Texas plant, at an implied $1,400/kW. NRG says it is developing 1.5 GW of new Texas gas for just above $1,000/kW, which values an operating plant about 40% above the stated cost of new build. The seller is shrinking its merchant gas position, with proceeds going to a buyback and debt reduction rather than replacement capacity.

Gaudette said the 1.2-GW combined-cycle plant NRG is building to power an unnamed cloud and AI hyperscaler's data center project is on track. He expects approved agreements and an announcement by year-end. NRG is advancing additional opportunities with the same customer, and the pipeline exceeds the turbine allocations and engineering, procurement and construction capacity under its original development agreement with GE Vernova and Kiewit, which NRG's earnings presentation puts at 5.4 GW of turbine capacity.

Asked about the midterm elections, Gaudette said "the political environment has actually strengthened this project and our projects," adding that he had spoken with the customer since the elections. "This project is going to happen." Texas elected a governor who promised to pause data center approvals, as Private Wealth Daily previously reported. Gaudette also said ERCOT power prices are depressed, an assumption built into NRG's 2027 guidance and long-term outlook.

The sale is expected to close in the second quarter of 2027, subject to regulatory approvals.

Half the $4B sale proceeds go to debt reduction

Uses of the $4B in sale proceeds, share of total, announced Nov. 9

  • Debt reduction50%50%
  • Stock buyback25%25%
  • Reinvestment flexibility25%25%
Source: NRG Energy earnings call, Nov. 9
Show as table
PartValueShare
Debt reduction50%50%
Stock buyback25%25%
Reinvestment flexibility25%25%

Reported by the Energy Transition desk from Utility Dive and NRG Energy deal announcement. Published . Updated Nov 17, 2026 · 8:14 a.m. ET. Corrections

Related

Infrastructure

LS Power closes $6bn private equity fund, earmarks $1.7bn for Constellation

COO Darpan Kapadia says demand growth is real and supply will take time to catch up.

Infrastructure

Google's flexibility alliance is a tariff play, not a software launch

Twenty-one organizations, two consultant reports and no disclosed capital: the AI Energy Management Alliance is buying standing in the resource plan, not curtailment revenue.

Infrastructure

GE Vernova to spend $34.5M on Shreveport transformer plant

The expansion is expected to lift the plant's workforce by nearly 30% and reach full capacity in 2028.

Infrastructure

Siemens Energy backlog hits €164 billion on turbine orders

US orders rose 70% in fiscal 2026 while data centers supply less than 10% of the order book.

Infrastructure

Google signs 50MW geothermal PPA with Quaise Energy

Project Obsidian near Bend, Oregon, starts supplying Google's The Dalles data centers in 2030 and could scale to 250MW.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections