Loudoun tables bill to strip approvals from 15 data center projects

The 15 grandfathered projects total roughly 10.5 million square feet across 30 buildings, and a companion audit measure also stalled.

At a glance

  1. The projects total roughly 10.5 million square feet across 30 buildings, ranging from just over 100,000 square feet to more than 4 million square feet.
  2. What the board tabled was a grandfather clause.
  3. Supervisors also tabled a second measure from the same two lawmakers, framed as a compromise, that would have required an audit of the legacy projects.

Loudoun County supervisors tabled a proposal Tuesday without a vote that would have stripped by-right zoning approvals from 15 data center projects, Bisnow reported.

The projects total roughly 10.5 million square feet across 30 buildings, ranging from just over 100,000 square feet to more than 4 million square feet. Bisnow identified Digital Realty’s Digital Dulles Phase 3 as the largest of the 15.

What the board tabled was a grandfather clause. Loudoun effectively ended by-right zoning for new data centers in March 2025, requiring even industrial-zone projects to win a special exception from the Board of Supervisors, according to Bisnow. Projects already in the approval pipeline kept the older path, and those 15 legacy projects are the ones advancing without the new review.

Supervisors also tabled a second measure from the same two lawmakers, framed as a compromise, that would have required an audit of the legacy projects.

Board Vice Chair Mike Turner, who voted against the original 2025 resolution, opposed the revocation. "I don't support changing grandfathering. To me, it's just unethical," Turner said at Tuesday's meeting. "We set the rules. Businesses made decisions based on those rules. We live by the rules."

Loudoun is the world's largest data center hub, with more than 250 facilities operating and more than 120 in the development pipeline, according to Bisnow, and much of the world's internet traffic passes through its eastern edge.

This publication has argued that entitlement, not power or land, is the binding constraint for Mid-Atlantic data center sponsors and their lenders. The 15 legacy projects sit in the largest hub with approvals already in hand, and a bill to revoke those approvals still reached the board.

Reported by the Sectors desk from Bisnow — Capital Markets. Published . Corrections

Related

Real Estate

Distressed commercial property sales rise 26.4% while nondistressed trades rise 50.3%

MSCI data cited by The Real Deal on Oct. 21 show $13.2 billion in distressed trades in the first nine months, up from $10.5 billion; overall volume rose nearly 50% to $560 billion.

Real Estate

Power tops US site-selection factors in consultants' survey as data center demand strains utilities

79% of surveyed consultants cite electric power as a top factor, ahead of labor availability and geopolitics at 50%.

Real Estate

B. Riley Securities doubts TKO's $2B unsolicited cash bid for SVC's remaining 93 hotels

One analyst estimates severing the Sonesta agreement alone would cost $535 million.

Real Estate

Thramann's LT350 plans data centers above parking lots

The startup plans one canopy build carrying solar, EV charging and GPU compute.

Real Estate

NYC Council passes COPA 38-9, giving nonprofits 70-day window

Sellers must notify HPD before listing a covered rent-stabilized building; the mayor is likely to sign, Commercial Observer reports.

Private Real Estate Dailyfrom Private Wealth Daily

Non-traded REITs, data centers, industrial and manager fundraising. Weekdays at 7:20 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections