Langenhorn council advances Uniq Land's 150MW data center plan

The August 26 vote opens planning studies, but a 300MW expansion and wind-powered supply depend on regional grid upgrades.

At a glance

  1. The outlet described the vote as provisional approval for a development proposed by Uniq Land and Erschließungsgesellschaft Nordfriesland (EG.NF).
  2. The decision opens a planning process, not a final approval.
  3. The vote followed consultation with residents who initially expressed hostility to the project.

Data Center Dynamics reported that the municipal council of Langenhorn in Schleswig-Holstein voted on August 26 to continue pursuing a data center with up to 150MW of connected load. The outlet described the vote as provisional approval for a development proposed by Uniq Land and Erschließungsgesellschaft Nordfriesland (EG.NF).

The decision opens a planning process, not a final approval. Uniq Land managing director Jens Kampkötter said studies still need to be prepared, the public will have further opportunities to give input, and the municipality will ultimately decide the conditions. "With the council's decision, we now have a clear planning process in place for Langenhorn," he told DCD. Uniq Land has applied to build in the district of Mönkebüll within the municipality, and local authorities have reserved the right to consider alternative sites in the area. Construction is set to begin in March 2028 at the earliest.

The vote followed consultation with residents who initially expressed hostility to the project. At the town hall meeting, residents criticized the proposed 27.5-meter (90ft) height of the two buildings and the transparency of the planning process, DCD reported. Municipal authorities will now assess the facility's impact on the surrounding landscape, its distance from residents, water use and potential noise. Kampkötter said the developer has taken on board concerns about distances to neighboring properties, building heights and noise.

Power, grid and remaining approvals

Power from regional wind farms and any expansion of the site's connection capacity to 300MW are both contingent on upgrades to the regional electricity grid, according to DataCenterInsider. The servers would be cooled using a waterless closed-loop system, and a waste heat reuse system is planned.

The August 26 vote leaves two main constraints: grid capacity and local consent.

Reported by the Data centers & fiber desk from Data Center Dynamics and DataCenterInsider. Published . Corrections

Related

Infrastructure

O3 Group plans Benghazi data center for March 2027

The Libyan operator gave no capital figure, capacity or named customer; international connectivity would use the Medusa cable.

Infrastructure

Meta has converted Ohio Facebook site into first phase of AI campus

The New Albany site is planned to scale to a gigawatt with roughly one million GPUs; it has already trained Meta's Muse models.

Infrastructure

Umatilla declares emergency over $5B data center permit freeze

The city resolution says the block could delay more than $5 billion in investment and set projects back two years.

Infrastructure

Umatilla permit freeze threatens $5 billion in data center investment

City says projects could be set back two years as BLM weighs 35 data center applications on western public land.

Infrastructure

Google and Voltus expand PJM virtual power plant to 1,170 MW

The expansion adds 1,070 MW to the June 100 MW program, with a three-to-four-year ramp and a 2040 term.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections