J.G. Petrucci files 100MW Allentown data center plan

The project's substation-first structure is a bet on power scarcity.

At a glance

  1. WFMX and Lehigh Valley Public Media first reported the filing, and Data Center Dynamics carried it.
  2. The property's prior life was a warehouse plan.
  3. J.G. Petrucci, founded in 1987, is a privately held developer with a portfolio of more than 7 million sq ft of commercial, industrial, and residential property across the Northeast.

J.G. Petrucci Company has submitted plans for a 100MW data center and an on-site substation at 1024 N. Bradford Street in Allentown, Pennsylvania, according to Frank Kane, the city's managing director. WFMX and Lehigh Valley Public Media first reported the filing, and Data Center Dynamics carried it. The building would span 146,000 sq ft. The Morning Call reports the company is in discussions with a potential end user, with construction potentially starting in early 2027 and the facility launching the same year.

The property's prior life was a warehouse plan. J.G. Petrucci secured planning approval in 2022 for a 146,000 sq ft industrial development called the Allentown Flex Center. The new filing pivots that approval toward data center use. That distinguishes it from the other big Allentown project: Quantum Group is converting an empty warehouse at 2401 W. Emaus Avenue into a roughly 250,000 sq ft data center. One project recycles a shell; the other re-purposes an approval.

J.G. Petrucci, founded in 1987, is a privately held developer with a portfolio of more than 7 million sq ft of commercial, industrial, and residential property across the Northeast. It already offers industrial space at Bethlehem's Lehigh Valley Industrial Park. The company did not comment to local press, according to DCD.

The filing has the look of a speculative build. No tenant is named; the only public reference is to a potential end user in discussions. A 100MW block of uncommitted power is a large position, and the proposed on-site substation is the most concrete commitment in the plan. At 100MW, substation work is a serious line item, and the proposal puts it on the schedule before a tenant is in hand. That suggests a developer willing to spend on grid access in the hope of securing a user before the steel goes up.

Pennsylvania's tightening window

The bet is being made as the state's rules shift. DC Byte's September 2025 analysis counted 7.8GW of planned data center load in Pennsylvania, up from 231MW of total IT load in 2021 — exponential growth, in the analyst firm's phrase. Governor Josh Shapiro signed an executive order this month imposing strict requirements on data center development, as DCD reported. The order's terms are not detailed in the coverage, so the effect on this project is unconfirmed. The direction, though, is toward more scrutiny.

The timeline reinforces the risk. Work starting in early 2027 and launching in the same year leaves little room for leasing after completion. That schedule assumes a tenant signs early or that the developer will carry empty capacity. The substation, once built, remains a fixed cost in the project's economics. It does not easily serve another use if the data center stalls.

The figures also point to the kind of tenant this design targets. 100MW across 146,000 sq ft implies a power density that suggests high-performance computing or AI training workloads. Those tenants are few, move slowly, and negotiate long. That makes the absence of an announced user more consequential, not less.

Whether the substation moves before a lease is signed tells you who is bearing the interconnection risk.

Pennsylvania has attracted a host of data center developments in recent months, according to DCD, and Allentown sits in that current. The city offers a mix of power access and industrial land, a combination that has drawn both the Quantum conversion and the Petrucci filing.

For private investors watching the data center land rush, the project is a reminder of where the durable value sits. Land and approvals are replaceable; a substation connected to the grid is an asset with a long, fixed life. Building one on spec is a statement that interconnection, not steel, is the scarce resource.

What matters now is sequence. Whether the substation moves before a lease is signed tells you who is bearing the interconnection risk. How the state's new rules affect permitting tells you whether the window is closing. J.G. Petrucci's filing puts both questions on the table. The substation is the part worth watching.

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Pennsylvania pulls AI data centers off the fast track

Governor Shapiro's order makes local sign-off and full-grid-cost payments prerequisites for state permits.

Infrastructure

Krolmap plans 225MW data center campus in Spain

Six buildings across 25 hectares in the La Legua industrial park; on-site generation would supply power, with capacity and tenants not yet published.

Infrastructure

Nvidia in talks to invest in Firmus after neocloud scrapped its IPO

The Information reports talks, not an agreement; a several hundred million dollar ticket would be a fraction of the $2bn–$3bn private raise Bloomberg reported Firmus was seeking.

Infrastructure

O3 Group plans Benghazi data center for March 2027

The Libyan operator gave no capital figure, capacity or named customer; international connectivity would use the Medusa cable.

Infrastructure

Meta has converted Ohio Facebook site into first phase of AI campus

The New Albany site is planned to scale to a gigawatt with roughly one million GPUs; it has already trained Meta's Muse models.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections