IURC approves AES Indiana's $1.3bn solar and storage project for Google data center

Google will cover all project costs, exceeding the 80% minimum Indiana's 2025 large-load data center law sets.

At a glance

  1. AES Indiana has said the project will cost approximately $1.3 billion to construct.
  2. The connection costs divide in two ways, according to local reporting cited by Data Center Dynamics.
  3. The contract between AES and Google will last at least 15 years and includes several provisions to prevent cost shifting onto regular ratepayers if Google decides to scale back or drop the project, Data Center Dynamics reports.

Indiana regulators have approved AES Indiana's plan to build solar, batteries and a transmission line to serve a Google data center in Monrovia. Google will pay all costs associated with the project, according to Data Center Dynamics, which reports it is the first data center filed under Indiana's 2025 large-load law. That law requires large-load data centers to cover at least 80 percent of the cost of the generation and transmission infrastructure built for them.

AES Indiana has said the project will cost approximately $1.3 billion to construct. Commissioner Joby Jerrells said the utility testified that Google would pay for at least 100 percent of the costs under the requirement. "Not only does this agreement satisfy the statutory requirement, it exceeds it substantially," Jerrells said.

The connection costs divide in two ways, according to local reporting cited by Data Center Dynamics. Gustavo Garaviglia, chief executive of AES US Utilities, said Google will pay $32.3 million for direct connection facilities, while $73.8 million in network upgrades will be included in AES's transmission rate base.

The contract between AES and Google will last at least 15 years and includes several provisions to prevent cost shifting onto regular ratepayers if Google decides to scale back or drop the project, Data Center Dynamics reports.

The build has three power components and one wire. Two standalone battery systems come in at 200MW and 130MW; a hybrid project pairs 130MW of solar with a 130MW battery; and a 10-mile (16-kilometer) 345kV line connects the project to an on-site substation near the data center. That substation is planned at 1,200MW, which suggests the interconnection is sized for more generation than this first filing covers.

Google's Indiana footprint extends beyond Monrovia. The company is also developing a campus in Fort Wayne, where it purchased 900 acres and committed around $2 billion, according to Data Center Dynamics. News that Google was behind the Monrovia development first emerged last October.

ComponentCapacity
Standalone battery storage200MW
Standalone battery storage130MW
Hybrid solar and battery130MW solar paired with 130MW battery
345kV transmission line10 miles (16 kilometers)
On-site substation (planned)1,200MW

Reported by the Energy Transition desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

SoftBank asks PJM to study 10-GW Ohio data center complex under state agreement

The filing pairs 9.6 GW of added load with 10.2 GW of SB Energy gas-fired generation through 2032 and three new AEP Ohio 765-kV lines.

Infrastructure

Cowboy Space asks FCC to approve 20,000-satellite Stampede after Google test craft reached orbit

The filing joins earlier proposals from SpaceX and Blue Origin and follows Google's Project Suncatcher, announced in November 2025, whose first test craft is now in orbit.

Infrastructure

Crusoe confirms Google as end user of its Goodnight campus in Texas

The Armstrong County project connects directly to two wind farms totaling 531MW, and Aterio Research puts the planned build at more than a gigawatt.

Infrastructure

Krolmap plans 225MW data center campus in Spain

Six buildings across 25 hectares in the La Legua industrial park; on-site generation would supply power, with capacity and tenants not yet published.

Infrastructure

Commerce signs $389m in power-semiconductor R&D letters of intent

Helion is in line for up to $175 million and Commonwealth Fusion Systems up to $85 million for fusion power electronics, Data Center Dynamics reports.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections