Israel's Electricity Authority caps new data center connection capacity at 200MW, with per-megawatt guarantees

The reported rules follow a queue of about 27GW of projects and require NIS 2 million ($643,300) in guarantees per megawatt requested.

At a glance

  1. Developers will have to provide guarantees of NIS 2 million ($643,300) for every megawatt of connection capacity they request.
  2. At the stated rate, a project requesting the full 200MW would need guarantees of about $129 million.
  3. NOGA, the national system operator, said it had about 27GW of projects seeking a grid connection.

Israel's Electricity Authority has capped new data center connection capacity at 200MW, Data Center Dynamics reported on 19 October, citing Calcalistech.

Developers will have to provide guarantees of NIS 2 million ($643,300) for every megawatt of connection capacity they request. They must also install backup mechanisms that allow data centers to be disconnected from the grid during periods of high demand.

At the stated rate, a project requesting the full 200MW would need guarantees of about $129 million.

NOGA, the national system operator, said it had about 27GW of projects seeking a grid connection. In July it issued a temporary order freezing responses to data center requests of 8MW or more. That freeze is expected to run until early December while the Electricity Authority, the Ministry of Energy and NOGA complete a joint review of how to divide power between data centers and the rest of the economy.

Alongside the cap, the authority said it would allocate an additional 1GW to large data centers, lifting the sector's contracted capacity above 3GW. If realized, that would account for around 20% of the country's electricity consumption in 2030.

Officials traced the surge in connection requests to the National Cyber Defense Bill, passed by the Knesset in February, which designated data centers as national infrastructure in order to remove planning and construction constraints. They described the cap and guarantee requirement as the policy response.

The report does not specify whether the 200MW cap applies per project, per site, or per developer, which determines whether a sponsor can stack multiple campuses inside the cap.

The rules are not final. A full decision is slated for publication in the coming days, following a three-week public consultation.

Israel's new 200MW data center cap against the grid queue

Capacity in megawatts

200 MWCap per new request3K MWData center capacity contracted27K MWProjects seeking grid connection200 MWCap per new request3K MW27K MWProjects seeking grid connection200 MWCap per new request3K MW27K MWProjects seeking grid connection
Source: Data Center Dynamics, citing Calcalistech · Oct
Show as table
LabelValue (MW)
Cap per new request200 MW
Data center capacity contracted3K MW
Projects seeking grid connection27K MW

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Crusoe plans 106MW Paraguay data center in first Latin America move

The site beside the Itaipú substation would serve Crusoe Cloud, with a first phase targeted for mid-2027.

Infrastructure

Crusoe and Polar DC to build 40MW second building at Norway campus

The Tørdal project sits beside a live 12MW facility hosting Crusoe Cloud AI infrastructure, though no construction timeline is given.

Infrastructure

Crusoe files for a $4.8bn data center campus in Jayton, Texas

The two buildings are slated to go live in 2029, and the filings name no tenant, landowner or power source.

Infrastructure

Aleria plans 8,640 Blackwell GPUs for 25MW US site

Aleria plans to expand the US build to 16,000 GPUs and calls the UAE Vera Rubin deployment one of the first in the region.

Infrastructure

Foresight signs term sheet for 50.01% of Polish data center developer

Warsaw is planned at 130MW on a secured 32,000 sqm plot with an option on a further 22,000 sqm.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections