At a glance
- Heron will make the units at Heron Factory One in Morgan Hill, California, a plant designed to produce up to 10,000 Heron Links a year, or more than 40GW of manufacturing capacity.
- Mass production at Heron Factory One is expected to start in late 2027, and each Heron Link is a 5MW modular converter, so 1.5GW implies roughly 300 units.
- For allocators underwriting data center assets, this puts a named supplier's production schedule inside the energization date.
Alphabet-owned Intersect reserved 1.5GW of solid-state medium-voltage transformers from Heron Power under a manufacturing capacity agreement, with deliveries expected to start in 2028, Data Center Dynamics reported.
Heron will make the units at Heron Factory One in Morgan Hill, California, a plant designed to produce up to 10,000 Heron Links a year, or more than 40GW of manufacturing capacity.
Mass production at Heron Factory One is expected to start in late 2027, and each Heron Link is a 5MW modular converter, so 1.5GW implies roughly 300 units.
For allocators underwriting data center assets, this puts a named supplier's production schedule inside the energization date. A project fitted with these units cannot come online before 2028. Heron's other data center agreements include more than 1GW of transformers for Vantage last month and a June letter of intent with Crusoe covering converter technology for the Stargate campus in Texas.
Heron was founded in 2024 by former Tesla senior executive Drew Baglino and is based in Scotts Valley, California. Intersect lists 2.2GW of operating solar PV and 2.4GWh of battery storage in operation or construction, mostly in Texas and California.
Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections