Gateway files 81MW Sydney data center plan

The former brickworks site would add five stories and 44 generators to a market where consent, not financing, now sets the buildout calendar.

At a glance

  1. New South Wales has already tied data center approval to a 40% wind-power purchase requirement — a rule this publication covered this month — and the SEARS application moves through that same regime.
  2. Gateway is not a firm known for data center development, and the gap between the AU$118.5m paid for the land in 2023 and the AU$1bn project ceiling suggests an industrial landlord trying to re-rate a warehouse estate as digital infrastructure.
  3. The filing puts 81MW in the queue, pending decisions that start with the state and end with the grid.

Gateway Capital, an Australian investment manager with AU$1.5bn under management and assets across Victoria, New South Wales, and Queensland, has filed a SEARS application with the New South Wales government for an 81MW data center in Sydney's St Leonards district, on the 1.8-hectare former brickworks site it bought from Dexus in 2023 for AU$118.5m (US$85.2m). First reported by the North Sydney Sun and carried by Data Center Dynamics, the filing covers a five-story building of 16,635 sqm at 12 Frederick Street with 11 data halls, 44 generators, an on-site substation, and up to AU$1bn (US$720m) of investment; documents describe the facility as constructed and operated by Gateway and Lendlease, the developer behind Sydney's Project Blue Tongue, a NextDC partnership in Adelaide, and a Tokyo project with PDG.

The 2023 acquisition, made through a joint venture with Invesco's Urban Infill Logistics, took an estate of 13 warehouse and office units covering roughly 19,400 sqm; the parcel now set aside for the data center holds two large multi-story warehouses, indoor recreation and office buildings, and car parking, while the broader area traces back to an 1800s brickworks before becoming industrial warehouses.

That 81MW figure makes this a planning event before a construction one: the data center buildout is no longer finance-constrained; it is consent-constrained. New South Wales has already tied data center approval to a 40% wind-power purchase requirement — a rule this publication covered this month — and the SEARS application moves through that same regime.

Gateway is not a firm known for data center development, and the gap between the AU$118.5m paid for the land in 2023 and the AU$1bn project ceiling suggests an industrial landlord trying to re-rate a warehouse estate as digital infrastructure. That trade depends entirely on whether the consent and the grid connection arrive. The filing puts 81MW in the queue, pending decisions that start with the state and end with the grid.

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

GreenSquare opens SYD1 phase one with Sharon AI as anchor tenant

The eight-month retrofit reused a 1995 IBM data center; a planned 80MW addition would take the Sydney campus to 110MW.

Infrastructure

Goodman withdraws 90MW Sydney data center application, citing policy shift

The AU$1.2 billion Lane Cove campus, in planning since March 2025, leaves the New South Wales queue while four other Sydney sites stay in development.

Infrastructure

GreenSquareDC signs Sharon AI for first stage of Sydney data center campus

Sharon AI expects to deploy about 8,200 Nvidia Blackwell Ultra GPUs at SYD1, with initial operations targeted for the fourth quarter of 2026.

Infrastructure

O3 Group plans Benghazi data center for March 2027

The Libyan operator gave no capital figure, capacity or named customer; international connectivity would use the Medusa cable.

Infrastructure

Meta has converted Ohio Facebook site into first phase of AI campus

The New Albany site is planned to scale to a gigawatt with roughly one million GPUs; it has already trained Meta's Muse models.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections