Fluor wins EPC contract for TeraWulf's $4 billion Kentucky campus

The definitive award covers three buildings at the Justified Data Campus, with ready-for-service completions phased from late 2027 into mid-2028.

$4BCost of TeraWulf's Justified Data Campus

At a glance

  1. Contract value was not disclosed, but early construction work has already started on site, ahead of settled pricing on the first two buildings.
  2. For investors underwriting the campus, the step from a preconstruction notice to a definitive contract commits Fluor through commissioning and sets a phased completion calendar.
  3. Kentucky utility regulators approved an electric-service agreement for the campus in August, Engineering News-Record reported.

Fluor won the definitive engineering, procurement and construction contract for three buildings at TeraWulf's $4 billion Justified Data Campus in Hawesville, Kentucky, the companies said in Nov. 4 releases.

Contract value was not disclosed, but early construction work has already started on site, ahead of settled pricing on the first two buildings. Fluor held a limited notice to proceed in March covering master planning and preconstruction. The definitive contract adds testing and commissioning, TeraWulf said in a separate Nov. 4 release. Fluor expects to recognize the award in the fourth quarter, once it finalizes pricing for the first two buildings.

For investors underwriting the campus, the step from a preconstruction notice to a definitive contract commits Fluor through commissioning and sets a phased completion calendar. Until Fluor sets pricing for the first two buildings, an allocator can compare the campus with others on schedule and power, but not on construction cost per building.

Kentucky utility regulators approved an electric-service agreement for the campus in August, Engineering News-Record reported. TeraWulf also secured credit support from Google for debt financing at the site. Anthropic holds about $19 billion in contracted lease commitments there, as Private Infrastructure Daily covered on Nov. 5.

"Fluor gives us the ability to scale execution without building a global engineering and construction organization internally," said Paul Prager, chairman and chief executive of TeraWulf.

TeraWulf expects ready-for-service completions to be phased from late 2027 through the second quarter of 2028, according to its release.

Fluor gives us the ability to scale execution without building a global engineering and construction organization internallyPaul Prager, chairman and chief executive of TeraWulf

Reported by the Data centers & fiber desk from Construction Dive and Engineering News-Record. Published . Corrections

Related

Infrastructure

Google backstops TeraWulf's 480MW Anthropic data center financing

The Justified campus in Kentucky is leased to Anthropic for 20 years under a $19 billion contract.

Infrastructure

TeraWulf to double Muskie contracted capacity to 1GW; second phase moves into 2029

The amended Kentucky Power agreement would raise contracted capacity at the Muskie Data Campus from 500MW to 1GW and pull the second 500MW phase forward a year, subject to state commission approval.

Infrastructure

Anthropic takes over $3.4bn Caterpillar generator order for 1.7GW

Texas supplier OnePWR will help install the 1.7GW of generators at Anthropic sites, with sets expected within two years.

Infrastructure

Nvidia pitches Apollo on up to 1GW of edge compute at Brightspeed

The Information reports the two are sharing information and arranging potential site visits, with first capacity possibly live as soon as Q1 2027.

Infrastructure

SpaceXAI seeks Arizona permit for 6GW data center campus

The Cochise County filing covers 747 acres and four 1.5GW stages, with a zoning decision due Dec. 9.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections