Skip to content
Friday, October 23, 2026 · Today’s edition, 6:30 a.m. ETFri, Oct 23 · 6:30 a.m. editionSign inMy Desk 0EditionsSign in

Fermi signs AMD credit support for first 222MW at Project Matador

AMD acts as guarantor while Fermi seeks financing for the initial build-out; a separate agreement frames expansion up to 650MW.

At a glance

  1. The agreement covers the first 222MW of IT capacity, with AMD acting as guarantor while Fermi seeks financing for the initial build-out.
  2. TensorWave is the customer of record at Matador, and AMD is its GPU vendor.
  3. Fermi's August deal with TensorWave covers up to 650MW of space at Matador, with the first 222MW expected online in the second half of 2027.

Fermi has signed a credit support agreement with AMD for the first data center at its Project Matador campus in Carson County, Texas, Data Center Dynamics reported. The agreement covers the first 222MW of IT capacity, with AMD acting as guarantor while Fermi seeks financing for the initial build-out.

TensorWave is the customer of record at Matador, and AMD is its GPU vendor. Thousands of AMD Instinct chips are slated to run AI training and inference workloads there, according to DCD, making the guarantee one from the equipment supplier rather than the tenant.

Fermi's August deal with TensorWave covers up to 650MW of space at Matador, with the first 222MW expected online in the second half of 2027. Fermi expects that contract to be worth up to $6.5 billion over 15 years. Both figures are ceilings; their ratio works out to roughly $667,000 per MW per year, an implied figure rather than a disclosed rate.

Fermi signed a second agreement with AMD alongside the credit support, outlining a partnership and a framework for future expansion of up to 650MW of gross power capacity. "Our strategic partnership establishes a framework for phases two and three," said Lee McIntire, Fermi's CEO. "We have the land, the permits, the water, the power equipment, and the fiber network that give us distinct performance advantages."

At full build-out, Project Matador could offer 17GW of data center space and an adjoining energy campus on land near Amarillo owned by the Texas Tech University system. The site could span 18 million sq ft (1.67 million sqm) and is intended to use a combination of on-site energy sources, including natural gas, solar, wind and nuclear. The 650MW expansion framework covers less than 4% of the 17GW potential, on DCD's figures.

"Our collaboration with Fermi is an important step in expanding the infrastructure capacity needed to bring next-generation AI solutions to market," said Mathew Hein, AMD's senior vice president and chief strategy officer of corporate development. He said the two companies are enabling customers to deploy AMD-powered AI infrastructure at scale.

In September this publication reported that Governor Greg Abbott's August halt on data center permits made community and ratepayer support part of project diligence and left 49.8GW of Texas projects waiting on a December audit deadline.

The first data center at Matador is due to be delivered next year, according to DCD.

Project Matador: 222MW first phase against a 17GW campus plan

Capacity in megawatts, from signed first data center to full build-out

222 MWFirst phase (AMD-backed)650 MWTensorWave contract ceiling17K MWCampus full build-out222 MWFirst phase (AMD-backed)650 MWTensorWave contract ceiling17K MWCampus full build-out222 MWFirst phase (AMD-backed)650 MW17K MWCampus full build-out
Source: Data Center Dynamics, Fermi and AMD disclosures
Show as table
LabelValue (MW)
First phase (AMD-backed)222 MW
TensorWave contract ceiling650 MW
Campus full build-out17K MW

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Ares and Astatine file SEC registrations for three pooled infrastructure vehicles

The vehicles list an undisclosed offering amount and $0 sold to date; SWI raised €800 million for data-center buildouts.

Infrastructure

Vultr plans 20MW of AMD Instinct MI355X GPUs in Chennai, India

Vultr calls it India's largest AMD Instinct deployment; the report did not name a host data center or capital figure.

Infrastructure

Samsung locks both Korean carriers into one AI-RAN vendor

Exclusive reference deployments at a shipyard and a petrochemical plant give Samsung first position on the software layer Korea's carriers will buy next.

Infrastructure

Switzerland publishes up to CHF 7bn government cloud tender

Two public-cloud tiers cap at CHF 2 billion each and the private lot at CHF 3 billion; awards due summer 2027.

Infrastructure

gFiber to take over Ting's Colorado Springs dark fiber lease

Terms were not disclosed; Ting will keep serving Colorado Springs customers until the transition completes, no later than June 30, 2027.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections