FERC keeps Oklo's 750-MW Virginia project out of PJM's queue

A procedural rejection leaves Oklo's three-technology plant at least 18 months behind and hands five similar complaints the same reasoning.

At a glance

  1. The project would connect at two Dominion Energy substations between Washington, D.C., and Richmond, and, according to Oklo's complaint, mixes 150 megawatts of advanced nuclear, 300 megawatts of fuel cells and 300 megawatts of gas-fired generation into a single application; losing the cycle would delay it by at least 18 months and raise its cost.
  2. FERC's order still told PJM that meeting growing regional demand requires it to collaborate with developers before, during and after the application process so that guidance and expectations are clearly understood, though none of that reopens the cycle.
  3. Oklo is not the only developer fighting those withdrawals: five other complaints are pending at FERC, brought by Advantage Capital Renewables, Agilitas Energy, Current Hydro, Lanyard Power Holdings and RWE Americas, each contending that PJM improperly dropped projects from the same cycle.

FERC rejected Oklo's complaint against PJM Interconnection on Thursday, declining to return a 750-megawatt Virginia project to the grid operator's current interconnection study cycle on procedural grounds: Oklo failed to show that PJM violated its tariff when it withdrew the project in early August, and did not resolve flaws in its application that PJM staff had identified.

The project would connect at two Dominion Energy substations between Washington, D.C., and Richmond, and, according to Oklo's complaint, mixes 150 megawatts of advanced nuclear, 300 megawatts of fuel cells and 300 megawatts of gas-fired generation into a single application; losing the cycle would delay it by at least 18 months and raise its cost.

FERC's order still told PJM that meeting growing regional demand requires it to collaborate with developers before, during and after the application process so that guidance and expectations are clearly understood, though none of that reopens the cycle. Oklo can fix the application and enter PJM's next study cycle, or take the Expedited Interconnection Track, whose window stays open until Dec. 31, 2027.

Oklo is not the only developer fighting those withdrawals: five other complaints are pending at FERC, brought by Advantage Capital Renewables, Agilitas Energy, Current Hydro, Lanyard Power Holdings and RWE Americas, each contending that PJM improperly dropped projects from the same cycle. The commission's reasoning here likely becomes the template for those dockets, which gives a procedural ruling an audience well beyond the 750 megawatts at stake. Pennsylvania regulators are already moving to price data-center access to that same grid, so Oklo's megawatts are now competing with load as much as with other generators.

As this publication has argued, power rights are the underwriting document now, and the queue and the utility tariff decide what gets built before capital does. This order is that argument stripped to its mechanics: FERC never weighed Oklo's reactor; it weighed the application, and a project split across nuclear, fuel cells and gas handed the grid operator three sets of assumptions to test. The design that hedged nuclear construction risk also multiplied the paperwork risk that cost it a cycle.

Oklo is commercializing metal-fueled fast reactors under its Aurora design, sized between 15 and 75 megawatts, so a 150-megawatt nuclear tranche implies more than one unit and the gas and fuel-cell blocks around it read as a bridge to first power. The choice ahead is narrow and dated: refile into the next cycle and absorb the 18 months, or take the expedited track before its window closes at the end of 2027.

Oklo's 750-MW Virginia project, by generation type

Advanced nuclear is 150 MW of a 750-MW application

150 MWAdvanced nuclear300 MWFuel cells300 MWGas-fired150 MWAdvanced nuclear300 MWFuel cells300 MWGas-fired150 MWAdvanced nuclear300 MW300 MWGas-fired
Source: Oklo complaint via Utility Dive
Show as table
LabelValue (MW)
Advanced nuclear150 MW
Fuel cells300 MW
Gas-fired300 MW

Reported by the Energy Transition desk from Utility Dive. Published . Corrections

Related

Infrastructure

How 230-kW AI racks are shifting data center capital to switchgear and rate design

Vertiv's 22,000-square-meter Slovakia expansion and Michigan's outcome-linked earnings proposal show where reliability money goes while Oklo's 750 MW sits out of PJM's queue after a FERC procedural rejection.

Infrastructure

PJM approves 2.1 GW of Engie storage and LS Power gas uprate

PJM expects the approved projects online by mid-2029; the expedited track that cleared them expires at the end of 2027.

Infrastructure

MISO asks FERC to approve penalty-free queue exits by Oct. 19

The filing would let 2022-cycle projects withdraw without penalty until Decision Point II on Oct. 20 and lift the network-upgrade cost trigger for later exits to 50%.

Infrastructure

Krolmap plans 225MW data center campus in Spain

Six buildings across 25 hectares in the La Legua industrial park; on-site generation would supply power, with capacity and tenants not yet published.

Infrastructure

Commerce signs $389m in power-semiconductor R&D letters of intent

Helion is in line for up to $175 million and Commonwealth Fusion Systems up to $85 million for fusion power electronics, Data Center Dynamics reports.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections