FERC approves Duke Energy Carolinas large-load rules with 15-year revenue terms

New or transferred large loads must pay a committed revenue contribution equal to 75% of the megawatt value in the load schedule for 15 years.

At a glance

  1. Utility Dive reported the approval on Oct.
  2. Under the approved provisions, FERC said the committed revenue contribution equals 75% of the megawatt value in the load schedule for each applicable month and year for 15 years after the upgrades enter service.
  3. A transmission customer that requires network upgrades to serve a new or transferred load also pays a monthly charge to cover the cost of building them.

FERC approved Duke Energy Carolinas' large-load transmission rules, requiring new or transferred large loads to pay a committed revenue contribution for 15 years after the network upgrades serving them enter service. Utility Dive reported the approval on Oct. 13.

Under the approved provisions, FERC said the committed revenue contribution equals 75% of the megawatt value in the load schedule for each applicable month and year for 15 years after the upgrades enter service. The terms go into the utility's pro forma network integration transmission service agreement, which Duke proposed revising on May 29 in response to growing large-load activity on its system.

A transmission customer that requires network upgrades to serve a new or transferred load also pays a monthly charge to cover the cost of building them. Once the upgrades are in service, Duke reimburses that customer for the costs plus interest, FERC said.

FERC asks Duke for more as RTO filings come due

The commission encouraged Duke to do more to protect existing customers from possible cost shifts, suggesting the utility consider individualized network integration agreements that offer greater protection than the pro forma agreement, or propose additional consumer protections to the just-approved document. "We encourage transmission providers — including [Duke Energy Carolinas] — to continually reevaluate their study processes and transmission service agreements," FERC said.

In his concurrence, Commissioner David Rosner called Duke's proposal "meaningful, if imperfect, new protections" and said consumer protections are "inadequate across the country."

The approval lands as FERC awaits proposals from regional transmission organizations and independent system operators, due next month, for beefing up their processes for interconnecting large loads such as data centers. Those filings respond to "show cause" orders the agency issued in June, which found RTO and ISO large-load interconnection rules appear inadequate, including for shielding existing customers from cost shifts when large loads require grid upgrades. The show cause orders do not cover Duke Energy Carolinas or other transmission owners outside RTOs and ISOs. Duke has about 3 million retail customers in the Carolinas.

As this publication reported in September, the data center buildout's power schedule is now a question of tariff design, and how a tariff allocates network-upgrade costs is what a load developer is underwriting long before a megawatt is delivered.

In his concurrence, Commissioner David Rosner called Duke's proposal "meaningful, if imperfect, new protections" and said consumer protections are "inadequate across the country."

Reported by the Energy Transition desk from Utility Dive. Published . Corrections

Related

Infrastructure

Enverus: SPP leads large-load readiness while PJM holds largest pipeline

SPP has the most advanced framework but about 5% of the high-confidence pipeline; PJM's 11.8 GW is 58% expected to be served behind the meter.

Infrastructure

NERC stakeholders back draft reliability rules for 50MW-plus compute loads

The draft covers 50 MW-plus AI data centers and crypto miners at 100 kV or above; the next step is the NERC board, then FERC.

Infrastructure

SoftBank asks PJM to study 10-GW Ohio data center complex under state agreement

The filing pairs 9.6 GW of added load with 10.2 GW of SB Energy gas-fired generation through 2032 and three new AEP Ohio 765-kV lines.

Infrastructure

Krolmap plans 225MW data center campus in Spain

Six buildings across 25 hectares in the La Legua industrial park; on-site generation would supply power, with capacity and tenants not yet published.

Infrastructure

Commerce signs $389m in power-semiconductor R&D letters of intent

Helion is in line for up to $175 million and Commonwealth Fusion Systems up to $85 million for fusion power electronics, Data Center Dynamics reports.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections

FERC approves Duke Energy Carolinas large-load rules with 15-year revenue terms — Private Wealth Daily