Equinix bookings climb 35% to $533M, guidance raised again

The company expects to exceed its 2026 retail capacity plan by nearly 40% and has presold more than 20% of fourth-quarter cabinets.

$533MRecord annualized gross bookings in Q3

At a glance

  1. Revenue was $2.571 billion, up 11%.
  2. Operating income rose 27% to $600 million and adjusted EBITDA rose 15% to $1.321 billion.
  3. For allocators underwriting the build, the presold share sets the near-term revenue test: Equinix must lease the remaining cabinets against a delivery plan that now overshoots by nearly 40%.

Equinix reported record annualized gross bookings of $533 million in the third quarter, up 35% from a year earlier, and raised full-year 2026 guidance for the third consecutive quarter. Revenue was $2.571 billion, up 11%.

Bookings grew three times faster than revenue

Annualized gross bookings and quarterly results, change vs. Q3 2025

Annualized bookings$533M+35%
Revenue$2.571B+11%
Operating income$600M+27%
Adj. EBITDA$1.321B+15%
Source: Company earnings release via Data Center Dynamics

Operating income rose 27% to $600 million and adjusted EBITDA rose 15% to $1.321 billion. Equinix said it has significantly increased the number of cabinets it plans to deliver in the second half of 2026 and expects to exceed its retail capacity plan for the full year by nearly 40%. More than 13,000 cabinets are scheduled for the fourth quarter, which the company describes as its highest quarter of delivery on record. More than 20% of that fourth-quarter capacity is presold, and 15% of the retail capacity coming online in 2027 is presold.

For allocators underwriting the build, the presold share sets the near-term revenue test: Equinix must lease the remaining cabinets against a delivery plan that now overshoots by nearly 40%.

Little of the new build is already leased

Share of planned capacity presold, as disclosed on the Q3 2026 call

Q4 2026 cabinets

>20%

2027 retail capacity

15%

The remainder must be leased against a delivery plan running nearly 40% above the full-year retail capacity plan.

Source: Company earnings call via Data Center Dynamics

Adaire Fox-Martin put developable capacity at 3GW, including projects in progress, with about 80% in Equinix's top 25 metros and land, power and permitting largely secured. The atNorth transaction completed in the quarter with CPP Investments brings an active development pipeline of 800MW due online over the next five years, plus a further 1GW of expansion opportunity.

"Capacity isn't simply a numbers game," Fox-Martin said on the earnings call. "A megawatt in a major interconnection hub is worth more than one elsewhere." New retail builds are generally sized at 60MW or less, she said, substantially smaller than the large-scale campuses drawing the most regulatory attention, and she noted that Equinix does not depend on any single build to meet its growth objectives. atNorth's Espoo addition, built under a €100 million Skanska contract, is due for completion in the third quarter of 2027, as Private Wealth Daily previously reported.

A megawatt in a major interconnection hub is worth more than one elsewhere.Adaire Fox-Martin, chief executive and president of Equinix

No single client accounts for more than 2.5% of total revenue, Fox-Martin said, meaning results do not rest on any one customer, industry, geography or technology trend.

Reported by the Data centers & fiber desk from Data Center Dynamics and Private Wealth Daily archive. Published . Corrections

Related

Infrastructure

atNorth tops out Espoo data center expansion under €100m Skanska contract

The five-story FIN02 addition began construction in April 2026 and is scheduled for completion in Q3 2027.

Infrastructure

atNorth plans €2 billion Salo data center with 75MW first phase

Power for the opening phase is secured and the grid connection could reach 230MW, with the campus due online in the third quarter of 2028.

Infrastructure

Kyivstar buys cloud provider GigaCloud for $50 million

About $5 million of the price is tied to operational milestones and capital spending met after close.

Infrastructure

FCC seeks comment on 482 MHz for direct-to-device service

The FCC also outlined plans to auction 25 MHz of mid-band spectrum, with a C-Band auction due by July.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections