Energa Obrót, CGE and Konin sign LOI for a 100MW data center in Poland

CGE estimates the staged project at just under €3 billion and says capacity could reach 260MW with municipal approval; no tenant or offtake terms are disclosed.

At a glance

  1. CGE is spearheading the development and will build it with JLL, the real estate consultant; both first-phase permits are already in hand, environmental consent from January 2026 and the building permit from that May, though the project was first proposed in April.
  2. Set against the 100MW first phase, CGE’s 20MW of own wind and solar leaves the coal plant and whatever on-site storage is added doing the heavy lifting — the practical version of the argument that grid access has become the asset and generation a derivative of permission.
  3. Three items are missing from the announcement, and they are the three that decide returns: a tenant, a price, and a capital stack.

Energa Obrót, the electricity retailer, has signed a letter of intent with renewable energy developer Central Energy Group and the municipality of Konin to develop a staged data center in the Polish city that CGE estimates at just under €3 billion ($3.4bn), with construction due to begin in early 2027 at 100MW of IT compute capacity and room to reach 260MW if the municipality approves further phases.

CGE is spearheading the development and will build it with JLL, the real estate consultant; both first-phase permits are already in hand, environmental consent from January 2026 and the building permit from that May, though the project was first proposed in April. That leaves the environmental clearance predating the proposal it clears, an ordering the announcement does not explain and one worth holding onto rather than smoothing over.

A coal plant carries the load

According to Inzynier budownictwa, the facility’s electricity needs will be met by the Konin coal-fired power plant, battery energy storage systems and several solar plants, while CGE brings its own generation in the form of a 2MW solar plant at Rychwał and an 18MW onshore wind farm at Kraśnica, two villages in central Poland; a district heating network that would siphon waste heat from the server rooms has also been proposed.

Set against the 100MW first phase, CGE’s 20MW of own wind and solar leaves the coal plant and whatever on-site storage is added doing the heavy lifting — the practical version of the argument that grid access has become the asset and generation a derivative of permission. The 12 underground fuel tanks point to on-site backup generation, though the disclosure does not name the equipment behind them.

A capacity number with no tenant

Three items are missing from the announcement, and they are the three that decide returns: a tenant, a price, and a capital stack. The €3 billion is an estimate of CGE’s investment, not a signed financing; no anchor tenant is named and no offtake terms are disclosed, and nothing assigns Energa Obrót a role beyond its signature, though the presence of an electricity retailer as a party to an LOI for a 260MW-capable campus suggests the company sits on the supply side of the power arrangement, though the coverage does not say so.

It is the same pattern this publication has flagged in renewable energy showing up in compute: a capacity number and a list of partners advance while the price column stays blank, and merchant risk settles on whoever ends up owning the asset. In Konin the blank is larger than usual, because a data center’s revenue begins with a tenant who has not been identified, and the first 100MW of a staged campus likely carries a disproportionate share of the fixed cost.

Poland has seen several large data center projects announced in recent months: Polcom, a cloud services operator, is developing a 40MW facility in Skawina, in the Lesser Poland Voivodeship — a project covered here in September, when the question was whether Polcom’s sovereign cloud could fill six halls before 2030, with Polcom itself as the anchor tenant — and farther north, WBS Power is spearheading a 3.2GW project in Choczewo, in Pomeranian Voivodeship.

At Konin, just under €3 billion spread across the eventual 260MW works out to roughly $13 million per megawatt of IT capacity; confined to the 100MW first phase, the same estimate is about $34 million a megawatt. Because that figure also covers offices, technical structures and fuel storage, it is not the per-megawatt build cost applied to Skawina — roughly $1 million a megawatt — and the comparison should not be pushed further than the numbers allow; what it establishes is that the estimate bundles land, permits, energy assets and shell into one number before anyone has signed for the compute.

Mayor Piotr Korytkowski welcomed the LOI as a step toward making Konin an AI hub for Poland and Europe and expects significant revenue from property taxes; the municipal arithmetic runs the other way as well, because the same body that granted the phase-one permits holds the decision on further phases, so 260MW is as much a Konin decision as a CGE plan.

The LOI schedules construction for early 2027, with 100MW before the municipality and another 160MW sitting behind its approval; the next document worth reading is the one that names a tenant, or the resolution that unlocks the phases beyond the first. Until one of them appears, the €3 billion remains an estimate attached to an intention.

Konin cost per megawatt: $34M at phase one, $13M at full build

The Konin estimate bundles land, permits, energy assets and shell; Skawina is build cost only

  • Konin, first 100MW phase$34M PER MW
  • Konin, full 260MW build$13M PER MW
  • Polcom, Skawina$1M PER MW
Source: CGE estimate via Data Center Dynamics; PWD archive · Sept 2026
Show as table
ItemValue ($M per MW)
Konin, first 100MW phase$34M PER MW
Konin, full 260MW build$13M PER MW
Polcom, Skawina$1M PER MW
a capacity number and a list of partners advance while the price column stays blank, and merchant risk settles on whoever ends up owning the asset

Reported by the Data centers & fiber desk from Data Center Dynamics, Property News.pl (via Data Center Dynamics) and Inzynier budownictwa (via Data Center Dynamics). Published . Corrections

Related

Infrastructure

Fink warns a US data center construction pause would cause recession

JLL estimates capacity through 2030 needs $3 trillion in investment; 77 percent of the construction pipeline is already pre-committed to tenants.

Infrastructure

Innova opens consultation on 148-acre Cheshire data center as residents object

The Spodegreen proposal on Tatton Estate farmland would draw grid power and include a solar farm, with a planning application expected late this year or early 2027.

Infrastructure

Walbridge's L5 Mission Critical hires JLL's data center chief

The new unit is selling the last unsold stretch of a build—the handoff from commissioning to energized capacity—at the moment delivery risk concentrates there.

Infrastructure

O-Green plans €7.4bn, 570MW data center campus in Spain

The Oman-affiliated fund's San Mateo de Gállego plan, reported to replace Vantage's €3.2bn project, holds grid permits for only its first 90MW phase.

Infrastructure

Aleria plans 8,640 Blackwell GPUs for 25MW US site

Aleria plans to expand the US build to 16,000 GPUs and calls the UAE Vera Rubin deployment one of the first in the region.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections