Duke Energy wins North Carolina data center rate class

Loads above 50MW face a 75% billing floor, 15-year contracts above 100MW and upfront interconnection payments from Jan. 1.

75%Minimum share of contracted demand billed

At a glance

  1. The class covers loads above 50MW, with a 15-year minimum contract for those above 100MW.
  2. For developers and their lenders, the terms turn a utilization-based power bill into a fixed obligation for the life of the contract.
  3. The rate structures are expected to raise annual costs by about 3.4% on average over two years for Duke Energy Progress customers and 3.7% for Duke Energy Carolinas customers.

The North Carolina Utilities Commission approved a separate Duke Energy rate class for data centers drawing more than 50MW, effective Jan. 1, Data Center Dynamics reported.

The class covers loads above 50MW, with a 15-year minimum contract for those above 100MW. Customers in the class pay a minimum billing threshold of 75% of contracted demand whether or not they consume it. They must also make upfront payments covering the estimated cost of direct grid interconnections, new transmission lines and upstream generation built to serve them. A stranded generation charge allocates the cost of plants built for a customer that exits early, and the rules allow interim curtailment during capacity shortages or grid stress.

For developers and their lenders, the terms turn a utilization-based power bill into a fixed obligation for the life of the contract. Upfront interconnection payments pull capital forward before revenue begins, and the curtailment provision adds operating risk to tenant leases. A campus sized below 50MW would sit outside the class, giving developers a threshold to design around.

The rate structures are expected to raise annual costs by about 3.4% on average over two years for Duke Energy Progress customers and 3.7% for Duke Energy Carolinas customers. Residential bills are expected to rise 4.7% and 4.8%, according to Data Center Dynamics.

North Carolina Attorney General Jeff Jackson proposed the new rate class in September. Kendal Bowman, Duke Energy's North Carolina president, said the outcome "keeps affordability at the forefront while allowing us to make the investments needed to strengthen reliability and support North Carolina's continued growth."

Residential bills rise more than the average

Expected rise in annual costs over two years, %

  • All customers
  • Residential
Source: Data Center Dynamics, citing approved Duke Energy rates
Show as table
GroupAll customersAll customers shareResidentialResidential share
Duke Energy Progress3.4%47.9%4.7%49.5%
Duke Energy Carolinas3.7%52.1%4.8%50.5%

Mid-Atlantic precedent

In October, FERC approved Duke Energy Carolinas large-load rules requiring a committed revenue contribution equal to 75% of the megawatt value in the load schedule for 15 years, as Private Wealth Daily previously reported. North Carolina joins Ohio and Virginia, among other states, in enforcing a large-load rate class, according to Data Center Dynamics.

The commission also ordered Duke to track data center service costs and operations as a separate customer class, to ensure transparency.

Reported by the Energy Transition desk from Data Center Dynamics and Private Wealth Daily archive: FERC approves Duke Energy Carolinas large-load rules. Published . Updated Nov 19, 2026 · 11:49 a.m. ET. Corrections

Related

Infrastructure

North Carolina just made the customer contract part of the permit

The commission refused a 255 MW turbine on a question of who the power serves, and that test now sits under Duke's $103 billion capital plan.

Infrastructure

Duke rate case freezes 2024 sales forecast as data center costs rise

Expert testimony for North Carolina's attorney general says 54% of the requested increase, about $1 billion a year, is tied to the frozen sales figure.

Infrastructure

Duke Energy's signed large-load agreements rise 200 MW to 7.8 GW

The utility plans a $103 billion buildout heavy on natural gas, with 7.6 GW of the 15.4 GW large-load pipeline still uncontracted.

Infrastructure

NERC winter outlook flags pipeline and transmission limits

NERC officials said single-fuel generators without long-term gas contracts may not run when winter demand peaks.

Infrastructure

DOE issues Grid United $2.8B conditional loan for Wyoming line

The 106-mile line would connect the Southwest Power Pool to the Western Electricity Coordinating Council and enter service in 2032 or 2033.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections