At a glance
- Utility Dive reported the commitment covers a roughly 106-mile line from a converter station in Platte County to an existing substation in Carbon County.
- For infrastructure allocators, federal credit support now attaches to a project that is still in permitting.
- Across its recent funding decisions, DOE could add about 7 GW of transfer capacity between the Western and Eastern interconnections.
The Department of Energy issued Grid United a $2.8 billion conditional loan commitment for the Wyoming Intertie, a 1.8-GW direct-current transmission line that would connect the Southwest Power Pool to the Western Electricity Coordinating Council.
Utility Dive reported the commitment covers a roughly 106-mile line from a converter station in Platte County to an existing substation in Carbon County. Terms beyond the commitment amount were not disclosed.
For infrastructure allocators, federal credit support now attaches to a project that is still in permitting. Grid United is developing three other lines between the interconnections, and DOE has recently agreed to help finance two of them, for about 6.6 GW of DOE-supported East-West capacity.
| Project | Capacity | Corridor |
|---|---|---|
| Wyoming Intertie | 1.8 GW | Wyoming (SPP to WECC) |
| North Plains Connector | 3 GW | North Dakota to Montana |
| Three Corners Connector | 1.8 GW | Oklahoma to Colorado |
| Pecos West | 1.5 GW | Texas (SPP) to New Mexico (WECC) |
Across its recent funding decisions, DOE could add about 7 GW of transfer capacity between the Western and Eastern interconnections. The department said in 2021 that 1,320 MW could flow between the two networks.
DOE said Tuesday the Wyoming Intertie could produce $39 billion in cost savings for ratepayers, help meet growing demand and improve grid resilience during high electric use and extreme weather. DOE's draft 2026 National Transmission Needs Study put average price differentials along the seam between SPP's eastern footprint and the Western Interconnection at $18/MWh to $33/MWh from 2012 to 2023.
Grid United expects to complete permitting in 2029 and begin construction in 2030, according to a company fact sheet. The company plans to bring the line online in 2032 or 2033, depending on procurement of HVDC equipment.
Reported by the Energy Transition desk from Utility Dive. Published . Corrections