At a glance
- The application, filed through Digital Golf Road LLC, calls for two two-story data center buildings totaling about 975,000 square feet and 156MW of IT capacity.
- Digital Realty already operates 175MW across nine facilities near Elk Grove Village and Franklin Park, according to Data Center Dynamics; the Rolling Meadows project would add 156MW, about 89% of that base.
- For allocators sizing Digital's Illinois exposure, the $81.5 million purchase price works out to about $522,000 per planned megawatt.
Digital Realty acquired a vacant office building in Rolling Meadows, Illinois, for $81.5 million in September and plans to demolish it for a 156MW data center campus, according to Data Center Dynamics.
The application, filed through Digital Golf Road LLC, calls for two two-story data center buildings totaling about 975,000 square feet and 156MW of IT capacity. A 240MW ComEd substation would sit on a separate 4.6-acre lot, 84MW above the campus's planned IT load, and the buildings would use closed-loop cooling to cut water consumption. The Rolling Meadows city council is scheduled to discuss the project this week.
Digital Realty already operates 175MW across nine facilities near Elk Grove Village and Franklin Park, according to Data Center Dynamics; the Rolling Meadows project would add 156MW, about 89% of that base.
For allocators sizing Digital's Illinois exposure, the $81.5 million purchase price works out to about $522,000 per planned megawatt.
The 40-acre site, about 25 miles northwest of Chicago, holds a 485,000-square-foot, three-story office building completed in 1998 that has been largely vacant since 2020. AT&T, 3Com, Capital One and the FAA were earlier tenants. Brennan Investment Group bought the property in 2023 to demolish it for a 600,000-square-foot industrial park, and Spear Street Capital acquired the site in 2010 for about $27 million.
Digital has also acquired the Hawthorne Race Course in Stickney, a 119-acre track that closed in July 2026, through Allimac 2023 LLC. Stickney Township has a six-month data center moratorium running to February 2027, and nearby Cicero has opposed data centers at the racetrack.
| Rolling Meadows site | Detail |
|---|---|
| Purchase price | $81.5 million, September 2026 |
| Site | 40 acres, 485,000 sq ft vacant office (built 1998) |
| Planned build | Two two-story buildings, about 975,000 sq ft |
| Planned IT capacity | 156MW |
| Power | 240MW ComEd substation on separate 4.6-acre lot |
| Next step | Rolling Meadows city council discussion this week |
Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections