Data center developers turn to legacy industrial sites as permitting tightens

Blackstart Digital's agreement to buy IBM's Almaden campus, with its 25MW substation, is the month's clearest case of a developer paying for power that already exists.

At a glance

  1. The price was not disclosed and the deal has not closed, but the campus carries two advantages a greenfield has to earn: zoning that is already settled and a substation that already exists.
  2. Blackstart plans to leave more than 500 acres undeveloped, holding land in reserve, avoiding the entitlement fight that developing it would require.
  3. The permitting environment has stopped being predictable: New York has imposed a statewide moratorium on new hyperscale data centers, and the industry's answer there has been behind-the-meter generation, fuel cells and storage, according to Data Center Dynamics, while contractors say Virginia, Pennsylvania and Texas have each constrained data center permitting since August.

Blackstart Digital's agreement to buy IBM's Almaden campus is the month's clearest case of a data center developer buying power that already exists, with more than 500 acres and a 25MW substation the company intends to expand. The price was not disclosed and the deal has not closed, but the campus carries two advantages a greenfield has to earn: zoning that is already settled and a substation that already exists. Blackstart plans to leave more than 500 acres undeveloped, holding land in reserve, avoiding the entitlement fight that developing it would require.

The permitting environment has stopped being predictable: New York has imposed a statewide moratorium on new hyperscale data centers, and the industry's answer there has been behind-the-meter generation, fuel cells and storage, according to Data Center Dynamics, while contractors say Virginia, Pennsylvania and Texas have each constrained data center permitting since August. Those accounts matter less for any single rule than for the shared shape of a longer path from site to shovel. The acoustics research of Kasey Fowler-Finn, a Saint Louis University biologist, opens a second front, recommending 1,500-foot setbacks over 4.5-foot walls on the finding that the 63-hertz hum of cooling systems passes through ordinary walls, which makes distance the practical mitigation and leaves a developer little to engineer against beyond the setback itself.

Reported by The Wrap desk from PWD data pack and deal log, Data Center Dynamics and Editorial brief — State of Infra Capital. Published . Corrections

Private Wealth Daily member access

Continue this analysis

Get the complete Infrastructure analysis and every detail that follows.

Enter a valid work email to continue reading.

Private Infrastructure Daily, from Private Wealth Daily. Unsubscribe anytime.

Full featuresIn-depth analysis and exclusive reporting.
Source-backed contextEvidence, context and the complete story.
One login across the networkAccess every Daily Network publication.

Related

Infrastructure

TeraWulf doubles Kentucky data center power contract to 1GW as utility financing tightens

Amazon's 690MW Calvert Cliffs nuclear PPA anchors a hyperscaler for two decades, while U.S. Bank warns utilities are turning to backup bank financing as DOE loans pull back.

Infrastructure

Jera, Dell and Rhaelm sign MoU for 400MW AI campus at Chiba gas plant

Apollo Global Management backs the first project, with operations targeted in or around 2028 and an estimated $15 billion across all phases.

Infrastructure

Xeal launches Laitent to run AI inference on idle EV charging capacity

The company says Laitent can reach more than 200MW of permitted electrical infrastructure across 1,600 US sites and plans 100,000 Nvidia GPUs.

Infrastructure

Google and Voltus expand PJM virtual power plant to 1,170 MW

The expansion adds 1,070 MW to the June 100 MW program, with a three-to-four-year ramp and a 2040 term.

Infrastructure

Anthropic in talks for second 460MW lease at Nscale's West Virginia campus

The reported $45 billion contract would double Anthropic's committed capacity at Monarch to 920MW; Microsoft already holds 1.35GW there.

From other sections