Data center construction spending climbs 8.6% in September

Data centers and power carried nonresidential construction to a sixth straight monthly gain, while other private nonresidential categories fell 7.8% over the year.

8.6%September data center construction spending, month over month

At a glance

  1. Spending has grown at a 217% annualized rate since May.
  2. The gain kept total nonresidential construction spending positive for a sixth straight month after a fifth consecutive advance in August, as Private Wealth Daily previously reported.
  3. For allocators underwriting compute or power assets, tariff-driven materials costs and supply-chain strain now belong in the same pro forma lines as land and interconnection.

Data center construction spending rose 8.6% from August to September, according to Associated Builders and Contractors figures reported by Construction Dive. Spending has grown at a 217% annualized rate since May.

The gain kept total nonresidential construction spending positive for a sixth straight month after a fifth consecutive advance in August, as Private Wealth Daily previously reported. Over the past year, data center construction spending is up 90%, according to a report from the Associated General Contractors of America, while private electric power investment rose 14% from September 2025. All other private nonresidential categories combined declined 7.8% over the same period, AGC found.

For allocators underwriting compute or power assets, tariff-driven materials costs and supply-chain strain now belong in the same pro forma lines as land and interconnection. AGC chief economist Ken Simonson said surging demand for data centers and power projects is "masking cutbacks in other investments" while adding to those supply-chain and cost strains.

ABC's Anirban Basu said, "Excluding data centers and the closely related power category, nonresidential spending actually fell in September." He expects the increases in data center and power construction to continue in the near term, citing recent rises in Treasury yields and ongoing materials price escalation as reasons AI-related project momentum should hold over the next several months.

Data centers rose 90% while the rest of the field fell

Year-over-year change in construction spending, %, Sept. 2025 to Sept. 2026

  • Above zero
  • Below zero
  • Data centers+90%
  • Private electric power+14%
  • All other private nonresidential−7.8%
Source: Associated General Contractors of America, via Construction Dive
Show as table
LabelValue (%)
Data centers+90%
Private electric power+14%
All other private nonresidential−7.8%
Excluding data centers and the closely related power category, nonresidential spending actually fell in September.Basu, in the Associated Builders and Contractors analysis

Reported by the Data centers & fiber desk from Construction Dive and Private Wealth Daily archive. Published . Corrections

Related

Infrastructure

Data center construction outruns the nonresidential field again as material and labor costs reemerge

Nonresidential construction spending rose for a fifth consecutive month in August, while ABC's chief economist expects momentum to stay confined to data centers and power.

Infrastructure

Data center work is the contractor market's dividing line

Contractors holding data center awards carry 9.9 months of backlog against 8.3 for those without, and the labor constraint trailing that work is starting to price into delivery schedules.

Infrastructure

The funding deadline moved to Dec. 11; the letting calendar did not

Congress gave surface transportation programs ten more weeks, leaving state DOTs and their bidders carrying the schedule risk they began hedging in July.

Infrastructure

Fermi's 222MW TensorWave lease misses closing deadline

Neither side has exercised termination rights, and the 222MW was not due until the second half of 2027.

Infrastructure

Fireworks signs for 5MW of Nvidia B300 capacity at Era4

The Chesterfield site runs primarily on landfill gas captured on site, with a grid connection as backup.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections