North America data center absorption hits 25GW record

A 65-point gap between AI support and local acceptance is the new constraint on supply.

At a glance

  1. The total is double the year-earlier figure and five times the level of two years prior.
  2. Vacancy has held at 1 percent for a third consecutive year despite what JLL calls unprecedented construction activity.
  3. The sustained 1 percent vacancy, even with that construction volume, suggests new space is being absorbed almost as quickly as it is delivered.

North America absorbed 25 gigawatts of data center capacity in the first half of 2026, an all-time high, according to JLL's Midyear 2026 North America Data Center Report, as covered by IREI. The total is double the year-earlier figure and five times the level of two years prior.

Vacancy has held at 1 percent for a third consecutive year despite what JLL calls unprecedented construction activity. The report counts 66 gigawatts of capacity under construction. At the current absorption pace, that book would be absorbed in roughly 16 months.

The sustained 1 percent vacancy, even with that construction volume, suggests new space is being absorbed almost as quickly as it is delivered. Annualized, the first-half absorption pace is 50 gigawatts a year.

The 65-point acceptance gap

Andy Cvengros, JLL's co-lead of U.S. data center markets, put it plainly: demand "continues to exceed even industry insiders' expectations." He attributes the pressure to hyperscalers, neoclouds and pure-play AI companies competing for scarce capacity, and calls community acceptance, or its absence, the defining challenge for the next phase.

The report measures the acceptance problem. 79 percent of Americans support U.S. leadership in artificial intelligence; 14 percent support data center development in their own community. The 65-point gap is where electricity, water and noise concerns turn into siting delays.

JLL argues that responsible growth depends on transparency and early community engagement around those impacts. For investors, that is the underwriting shift: absorption numbers now matter less than permission. The record demand is real, but the question the market faces is how much of it can actually be built.

Reported by the Sectors desk from IREI. Published . Corrections

Related

Real Estate

KKR supplies $95 million 10-year loan for Brooklyn apartments

Bridge, Declaration Partners and Avery Hall are the sponsors; coupon and spread were not disclosed.

Real Estate

Manhattan trophy office vacancy falls to 4.9% cycle low

JLL finds $300-per-square-foot leases arrived three times faster than the $200 benchmark, with new supply projected to fall to 1.5 million square feet a year.

Real Estate

Grover Corlew buys 200 East Broward in Fort Lauderdale for $69.7 million

The Boca Raton buyer plans $20 million in amenities for the 75 percent-occupied, 1991-vintage tower.

Real Estate

Thramann's LT350 plans data centers above parking lots

The startup plans one canopy build carrying solar, EV charging and GPU compute.

Real Estate

NYC Council passes COPA 38-9, giving nonprofits 70-day window

Sellers must notify HPD before listing a covered rent-stabilized building; the mayor is likely to sign, Commercial Observer reports.

Private Real Estate Dailyfrom Private Wealth Daily

Non-traded REITs, data centers, industrial and manager fundraising. Weekdays at 7:20 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections