Colt DCS and RMZ start 64MW Mumbai 3 build after hyperscaler lease

Once online, the campus will total 86MW, with 148MW possible at full build-out.

At a glance

  1. Mumbai 3 will pair conventional air cooling with direct liquid-to-chip cooling and use a closed-loop system intended to reduce water use, according to Data Center Dynamics, which reported the construction start.
  2. The construction start sits inside a $1.7 billion joint venture the two firms announced in 2024, through which they have committed to develop 250MW across Mumbai and Chennai.
  3. Colt DCS lists 15 operational data centers and 12 more under development across nine cities in the UK, Europe and Asia-Pacific.

Colt Data Centre Services and RMZ said this week that construction has started on Mumbai 3, a 64MW building at their Navi Mumbai campus, after signing a hyperscale customer.

Once the building is online, the campus's three buildings will total 86MW; at full build-out the Navi Mumbai site could reach 148MW. Mumbai 3 will pair conventional air cooling with direct liquid-to-chip cooling and use a closed-loop system intended to reduce water use, according to Data Center Dynamics, which reported the construction start.

The construction start sits inside a $1.7 billion joint venture the two firms announced in 2024, through which they have committed to develop 250MW across Mumbai and Chennai. The pair are also considering a project in Vizag, according to the report.

Colt DCS lists 15 operational data centers and 12 more under development across nine cities in the UK, Europe and Asia-Pacific. The company says it has nearly 800MW of capacity under development, a pipeline overseen by CEO Quy Nguyen, named permanent chief executive in August, as this publication reported. Fidelity Investments has owned Colt since 2015.

Navi Mumbai campus: 64MW new building, 148MW at full build-out

Capacity by stage of development (cumulative)

64 MWMumbai 3 (on completion)86 MWCampus with Mumbai 3 online148 MWCampus at full build-out64 MWMumbai 3 (on completion)86 MWCampus with Mumbai 3 online148 MWCampus at full build-out64 MWMumbai 3 (on completion)86 MW148 MWCampus at full build-out
Source: Data Center Dynamics report on Colt DCS / RMZ Navi Mumbai campus
Show as table
LabelValue (MW)
Mumbai 3 (on completion)64 MW
Campus with Mumbai 3 online86 MW
Campus at full build-out148 MW

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Colt DCS names Quy Nguyen permanent CEO after acting stint

The appointment ends a months-long acting stint and puts nearly 800MW of development squarely on Nguyen's plate.

Advisors

Allianz survey finds 34% of Americans expect Medicare to cover long-term care

The survey of 1,000 adults also found 23% believe Medicare is free; Fidelity projects $185,000 in retirement medical costs, excluding long-term care.

Retirement

Devenir: invested HSA balances top $100 billion, 52% of assets

Only 11% of HSAs hold investments, yet they account for 59% of HSA assets.

Infrastructure

European Commission accuses KKR of misleading €22bn TIM NetCo merger review

The Statement of Objections alleges KKR misstated whether FiberCop's wholesale access terms were locked in place; KKR says it stands by the information it gave.

Infrastructure

Memphis City Council rejects 18-month data center moratorium, sets 135-day pause

The 18-month ban failed on a 6-6 vote with one member absent; the 135-day pause is tied to Mayor Paul Young's 90-day review.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections