Broadcom organizes $63B loan for Anthropic TPU purchases

Bank of America, Citi and Morgan Stanley arrange the first lien; Blackstone takes the committed second lien and Broadcom backstops the SPV.

$63BSPV loan arranged for Anthropic TPU purchases

Watch

Anthropic Might Be Proving the AI Bears Wrong

The Compound (Ritholtz Wealth)Video2 min

At a glance

  1. The financing, called Project North Star, is part of a previously announced strategic compute capacity agreement, with delivery of the semiconductors expected to start in 2027.
  2. Bank of America, Citi and Morgan Stanley arrange the first-lien portion, while Blackstone is the sole provider of the committed second-lien tranche, according to IREI.
  3. For Broadcom equity and bond holders, that residual-value support makes the chipmaker a backstop to the SPV on an amount equal to the first lien before hardware is delivered in 2027.

Bank of America, Citi, Morgan Stanley and Blackstone are arranging a $63 billion loan through a special-purpose vehicle to fund Anthropic's purchase of Broadcom-developed Google TPUs, Data Center Dynamics reported. The financing, called Project North Star, is part of a previously announced strategic compute capacity agreement, with delivery of the semiconductors expected to start in 2027.

Bank of America, Citi and Morgan Stanley arrange the first-lien portion, while Blackstone is the sole provider of the committed second-lien tranche, according to IREI. Broadcom is providing residual value support to the SPV equal to the first-lien amount. A Wall Street Journal report cited by Data Center Dynamics said CEO Hock Tan spent two months organizing the financing and that the banks accepted higher interest rates in exchange for guarantees protecting them from losses if Anthropic defaults.

For Broadcom equity and bond holders, that residual-value support makes the chipmaker a backstop to the SPV on an amount equal to the first lien before hardware is delivered in 2027. The recovery question turns on the SPV. IREI says the financing supports hardware to be leased to Anthropic, while Data Center Dynamics frames it as Anthropic's purchase. That changes whether lenders recover equipment inside the vehicle or a claim on Anthropic's balance sheet.

Anthropic in April 2026 said it had signed a deal with Broadcom and Google for 3.5GW of Google TPUs coming online from 2027, with the vast majority of the new compute in the United States, Data Center Dynamics reported. Anthropic described that capacity as part of a November 2025 pledge to invest $50 billion in US compute infrastructure.

Anthropic filed its S-1 on Oct. 26, disclosing $417 billion in compute commitments as of December 2025, as Private Wealth Daily previously reported. It reported $6.2 billion of debt and plans to list on Nasdaq under the symbol ANT. The $63 billion facility is about ten times the debt the filing reports, though whether it lands on Anthropic's balance sheet depends on whether the SPV owns the hardware and leases it, as IREI describes, or Anthropic buys it outright, as Data Center Dynamics describes.

Anthropic's commitments dwarf the $63B chip financing

Dollar amounts in $B: compute commitments (Dec 2025), the facility, the US pledge, reported debt

  • Compute commitments$417B
  • North Star facility$63B
  • US compute pledge$50B
  • Debt in S-1$6.2B
Source: Anthropic S-1 via Data Center Dynamics; IREI
Show as table
ItemValue ($B)
Compute commitments$417B
North Star facility$63B
US compute pledge$50B
Debt in S-1$6.2B

Reported by the Data centers & fiber desk from Data Center Dynamics, IREI and Wall Street Journal, as cited by Data Center Dynamics. Published . Updated Oct 28, 2026 · 8:58 a.m. ET. Corrections

Related

Infrastructure

SpaceXAI seeks Arizona permit for 6GW data center campus

The Cochise County filing covers 747 acres and four 1.5GW stages, with a zoning decision due Dec. 9.

Infrastructure

Google backstops TeraWulf's 480MW Anthropic data center financing

The Justified campus in Kentucky is leased to Anthropic for 20 years under a $19 billion contract.

Infrastructure

Anthropic discloses $895.4bn in compute and data center commitments

Google, SpaceX, Amazon and Microsoft account for $396.7 billion of the total, and three of those four contracts are payable regardless of usage.

Infrastructure

Google commits $17 billion to Wyoming data center campus

The Cheyenne site combines a 702 MW AEP-owned fuel-cell array, gas generation from Tallgrass and Black Hills, and a CO2 sequestration hub.

Infrastructure

Microsoft design change pushes Iren's $4 billion ARR start to January

The network upgrade sits outside the original contract scope, Iren says, and supplier delays could push the revenue start to end-February.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections