Box2Bit transfers 150MW of grid capacity to Blackstone

The Épila withdrawal is the third Aragón campus Capital Energy's Box2Bit has abandoned.

At a glance

  1. Investment at Blackstone's Calatorao campus now exceeds €13 billion ($14.3 billion), according to El Español, as cited by Data Center Dynamics, up from €7.5 billion ($8.2 billion) and 300MW at the initial announcement.
  2. For allocators underwriting Spanish data center pipelines, Data Center Dynamics reports grid availability has become the primary criterion in due diligence, ahead of the land parcel or the declaration of public interest.
  3. Data Center Dynamics reported Box2Bit had already canceled the €3.4 billion ($3.75 billion) Ebro campus in Cariñena and the €1 billion ($1.1 billion) La Charluca site in Calatayud.

Box2Bit is transferring 150MW of grid connection capacity to Blackstone and withdrawing from Epilon, its data center project in Épila, Spain, Data Center Dynamics reported Nov. 13.

Investment at Blackstone's Calatorao campus now exceeds €13 billion ($14.3 billion), according to El Español, as cited by Data Center Dynamics, up from €7.5 billion ($8.2 billion) and 300MW at the initial announcement. The campus has final planning permission and is planned for 430MW in two phases. The price Blackstone paid for the 150MW was not disclosed, according to Data Center Dynamics.

For allocators underwriting Spanish data center pipelines, Data Center Dynamics reports grid availability has become the primary criterion in due diligence, ahead of the land parcel or the declaration of public interest. The 150MW changed hands while owners of roughly 100 hectares reserved for Epilon have not been paid, according to the report.

Data Center Dynamics reported Box2Bit had already canceled the €3.4 billion ($3.75 billion) Ebro campus in Cariñena and the €1 billion ($1.1 billion) La Charluca site in Calatayud. The Cariñena project was ruled out for falling outside the Ministry's grid investment plan; La Charluca failed to secure transmission access, and self-consumption alternatives did not materialize. Red Eléctrica denied CPD Edge Solutions, a Box2Bit subsidiary, access for consumption at the Calatorao 220 kV substation.

Jesús Bazán, the mayor of Épila, suggested speculative operations could be at work: "announcing a project, securing land and connection rights, and then transferring the connection without building." Bazán said Box2Bit failed to make the first payment on the land, and its rights expired in May, four months after the Government of Aragón declared the project to be of public interest.

Épila's first phase had been scheduled to go live in 2029; the 150MW meant to serve it now supports the Calatorao campus.

Blackstone's Calatorao investment nearly doubled to €13B

Investment in the Calatorao data center campus, € billion, at announcement vs now

Initial announcement

€7.5B

Now

€13B

The price paid for the 150MW of grid capacity was not disclosed.

Source: El Español via Data Center Dynamics

Reported by the Data centers & fiber desk from Data Center Dynamics and Data Center Dynamics. Published . Updated Nov 16, 2026 · 7:32 a.m. ET. Corrections

Related

Infrastructure

AirTrunk and Stockland cancel Sydney data center plans

Quantum DC's Tungkillo project is paused, and AirTrunk called its Lane Cove West site unsuitable.

Infrastructure

AirTrunk signs Hunter renewables exclusivity with European Energy

Solar and battery output are expected in 2030, with wind following in 2032.

Infrastructure

Rowan raises $1.5bn corporate credit for data center pipeline

Citibank led the $590 million revolver and $355 million letter of credit while Apterra led a $600 million term-loan upsize.

Infrastructure

Orennia estimates 191 GW of planned data center capacity at risk

Exposure after the midterms concentrates in Texas, Ohio and Georgia, where incoming Democratic governors campaigned on restricting construction.

Infrastructure

Optimum skips $102.5m in interest payments on $22bn debt

CSC Holdings has until around Dec. 16 before the missed payment counts as a default, and a steering committee of debtholders is negotiating a restructuring.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections

Box2Bit transfers 150MW of grid capacity to Blackstone