Blue Owl preps $513M CMBS on Amazon-leased data center

Citigroup is arranging the single-asset loan, whose $375 million top tranche carries initial guidance of about 195 basis points over benchmark, per Private Equity Wire.

$513MSingle-asset CMBS loan on Amazon-leased data center

At a glance

  1. The collateral is the 54-megawatt Project Crossing III in Gainesville, Va.
  2. The deal stacks three tranches, Private Equity Wire reported: a $375 million slice expected to be rated AAA, a $112 million slice at AA and a $26 million slice placed privately.
  3. For debt allocators, the guidance provides a live mark: about 195 basis points over benchmark for the AAA slice and about 260 for the AA, on a loan whose only rent payer is Amazon.

Blue Owl Capital is preparing a $513 million single-asset CMBS deal backed by a Northern Virginia data center leased to Amazon, according to Bloomberg, which cited people familiar with the transaction. Citigroup is arranging the financing, Private Equity Wire reported. The collateral is the 54-megawatt Project Crossing III in Gainesville, Va.

The deal stacks three tranches, Private Equity Wire reported: a $375 million slice expected to be rated AAA, a $112 million slice at AA and a $26 million slice placed privately. The AAA slice carries initial pricing guidance of about 195 basis points over benchmark, and the AA about 260. The top two tranches have an average life of about five years. Fitch Ratings and Kroll Bond Rating Agency are the expected raters on the senior piece. Kroll is the expected rater on the other two.

For debt allocators, the guidance provides a live mark: about 195 basis points over benchmark for the AAA slice and about 260 for the AA, on a loan whose only rent payer is Amazon. The risk being priced is one lease in one building. Loudoun County's 12-month moratorium on new data center applications, if it holds, limits the competing supply that would otherwise get built around it.

Blue Owl Digital Infrastructure Trust bought the 363,220-square-foot building for $779.5 million, Commercial Observer reported. The Amazon lease runs through 2042 with two five-year renewal options, per Commercial Observer, though Private Equity Wire put the expiration at 2041. Project Crossing III is the third of five planned buildings at the Gainesville Crossing campus, a 326-megawatt development by Corscale Data Centers and Affinius Capital.

As Private Wealth Daily previously reported, Citibank and Wells Fargo wrote a $512.6 million floating-rate mortgage due December 2028 against the purchase, with Blue Owl funding the balance from cash. The $513 million securitization is within $400,000 of that loan, suggesting the CMBS takes out the bank mortgage. Bloomberg reported the proceeds would finance the acquisition. In June, Blue Owl lent $975 million to Corscale and Affinius to recapitalize the building, Commercial Observer reported.

Michael Lascher, Blue Owl's head of capital markets and asset management, told NYU's Schack Institute capital markets conference in Manhattan on Wednesday that tighter construction conditions lift the value of what already stands. "What it does do is make what is already built more valuable because there are higher barriers to building more," he said.

Three-quarters of the $513M deal is AAA

Tranche size in $M; AAA guidance 195bp and AA 260bp over benchmark

  • AAA73.1%$375M
  • AA21.8%$112M
  • Private5.1%$26M
Source: Private Equity Wire; Commercial Observer
Show as table
PartValueShare
AAA$375M73.1%
AA$112M21.8%
Private$26M5.1%
What it does do is make what is already built more valuable because there are higher barriers to building more.Michael Lascher, head of capital markets and asset management at Blue Owl

Reported by the Real estate debt desk from Commercial Observer, Private Equity Wire and Bloomberg (via Commercial Observer and Private Equity Wire). Published . Corrections

Related

Real Estate

Blue Owl trust buys Virginia data center for $779.5M

Citibank and Wells Fargo wrote a $512.6 million floating-rate mortgage due December 2028, with Blue Owl funding the rest from cash.

Real Estate

Nvidia pitches insurers on backing neocloud GPU loans as lenders balk

The Financial Times reports early talks with no agreements in place, as AI cloud tenants take a growing share of Nvidia's demand.

Real Estate

Bain report sizes the $4.2 trillion AI revenue gap behind data center capex

Bain & Co. estimates existing consumer and enterprise AI can cover up to $1.8 trillion of the $6 trillion in annual revenue it says the industry must generate by 2031.

Real Estate

MMCC arranges $10.2M bank loan on 1M sq ft mill

The 10-year loan on the 1847 Whitin Machine Works carries a 6.85% rate, 75% loan-to-value and 25-year amortization.

Real Estate

Walker & Dunlop arranges $270M Journal Square refinancing

Apollo affiliates provide a floating-rate, interest-only bridge for Nasser Freres' Journal Square tower as it moves from construction to stabilized operations.

Private Real Estate Dailyfrom Private Wealth Daily

Non-traded REITs, data centers, industrial and manager fundraising. Daily at 7:20 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections