Ares-backed Ada breaks ground, but 300MW gap looms

The third TKW1 building is underway, but Ada's named pipeline covers only two-thirds of its 900MW Japan target.

At a glance

  1. Work on the first building began in August 2023 and was scheduled to go live in May 2025; the second, started in May 2024, is expected to follow in 2027.
  2. Ras Scollay, principal for revenue and product in APAC, called the ceremony the firm's third groundbreaking and its second in Tokyo in four months, adding that "Ada is truly moving at an unprecedented pace."
  3. Ada's stated ambition is roughly $12 billion over five years to deliver 900MW of data center capacity in Japan, but the published pipeline currently names five campuses totaling 600MW: four in Tokyo, designated TKW1, TKW2, TKE1 and TKE2, plus one in Osaka.

Ada Infrastructure has broken ground on the third and final building at its TKW1 data center campus in Tokyo, an 11MW addition to two 10MW predecessors that brings the site to 31MW and, according to the company's LinkedIn post, marks its fifth project in Japan and its second Tokyo groundbreaking in four months. Work on the first building began in August 2023 and was scheduled to go live in May 2025; the second, started in May 2024, is expected to follow in 2027.

Ras Scollay, principal for revenue and product in APAC, called the ceremony the firm's third groundbreaking and its second in Tokyo in four months, adding that "Ada is truly moving at an unprecedented pace." The pace rests on a relatively young corporate structure: Ada was set up in 2023 by Singapore-based logistics real estate firm GLP to develop and hold its data center assets outside China, and Ares acquired it alongside GLP's other international assets the following year, making Ares the owner of the Japanese buildout.

Ada's stated ambition is roughly $12 billion over five years to deliver 900MW of data center capacity in Japan, but the published pipeline currently names five campuses totaling 600MW: four in Tokyo, designated TKW1, TKW2, TKE1 and TKE2, plus one in Osaka. On three of those Tokyo sites the numbers are explicit: TKW2 is planned at 295MW across eight five-story buildings by 2026, TKE1 at 66MW across three four-story buildings by 2026, and TKE2 at 190MW across four four-story buildings starting in 2027, while Ada is also developing projects in the UK and Brazil.

That leaves roughly 300MW of Japanese capacity—a third of the target and roughly the size of another TKW2—absent from the named pipeline. Grid access has become the binding constraint of the digital buildout, with power and interconnection rather than shovels now setting the schedule, so Ada's two Tokyo groundbreakings in four months show it can secure sites and start construction but say little about whether the unallocated 300MW will ever be built. The next round of site announcements will reveal how much of that remaining capacity comes with actual interconnection rights behind it.

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Ares secondaries funds lift Sabey data center commitment past $500 million

Sabey and National Real Estate Advisors disclosed the follow-on three months after Ares's July 2026 minority stake; no size or terms were given.

Infrastructure

Ares and Astatine file SEC registrations for three pooled infrastructure vehicles

The vehicles list an undisclosed offering amount and $0 sold to date; SWI raised €800 million for data-center buildouts.

Infrastructure

TeraWulf doubles Kentucky data center power contract to 1GW as utility financing tightens

Amazon's 690MW Calvert Cliffs nuclear PPA anchors a hyperscaler for two decades, while U.S. Bank warns utilities are turning to backup bank financing as DOE loans pull back.

Infrastructure

O3 Group plans Benghazi data center for March 2027

The Libyan operator gave no capital figure, capacity or named customer; international connectivity would use the Medusa cable.

Infrastructure

Meta has converted Ohio Facebook site into first phase of AI campus

The New Albany site is planned to scale to a gigawatt with roughly one million GPUs; it has already trained Meta's Muse models.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Weekdays at 7:25 a.m. ET.

Free. Weekday mornings. Unsubscribe from any edition in one click.

From other sections