Applied Digital readies first 25MW hall at Polaris Forge 2

Base-build commissioning is complete for 75MW of the campus's first 150MW building, with 50MW still to be fitted out.

At a glance

  1. The 1GW plan's leasing risk sits in the gap between the 200MW under contract and the remaining 800MW the tenant can claim under its right of first refusal.
  2. The campus is largely leased to an unnamed investment-grade hyperscaler, which signed a 15-year agreement for 200MW in October 2025.
  3. The milestone follows delivery of 250MW of operational critical IT load at Polaris Forge 1 in Ellendale, North Dakota.

Applied Digital said on Nov. 24 that the first 25MW data hall at Polaris Forge 2 in Harwood, North Dakota, is ready for service, Data Center Dynamics reported.

Base-build commissioning is complete for the first 75MW of the campus's initial 150MW building, leaving the remaining 50MW still to be fitted out and delivered to the customer.

The 1GW plan's leasing risk sits in the gap between the 200MW under contract and the remaining 800MW the tenant can claim under its right of first refusal.

The campus is largely leased to an unnamed investment-grade hyperscaler, which signed a 15-year agreement for 200MW in October 2025. The same tenant holds a right of first refusal on up to 800MW more at the site, and Polaris Forge 2 is planned for 1GW across 900 acres.

The milestone follows delivery of 250MW of operational critical IT load at Polaris Forge 1 in Ellendale, North Dakota.

"AI infrastructure demand is not theoretical for us. It's backed by long-term customer commitments, and our focus is on delivering against them," said Wes Cummins, chairman and CEO of Applied Digital. Cummins said the second campus reaching ready for service on schedule shows the execution model is repeatable.

Earlier this week Applied Digital disclosed an 18-year capacity agreement with a second investment-grade hyperscaler, with base-term revenue of $5.4 billion, as Private Wealth Daily previously reported. The base-term revenue rises to $12.7 billion if all renewal options are exercised over a potential 33 years. That contract took total contracted base-term revenue above $41 billion, or $100 billion with all renewals, and the portfolio to more than 1.6GW of contracted critical IT load and 2.2GW of grid-connected peak load.

Voters in Harwood rejected a data center permit rule with 75.6% this month, leaving the proposed 1GW campus on its existing permitting path, as Private Wealth Daily previously reported.

Only 200MW of the 1GW site is under contract

Polaris Forge 2 planned capacity by lease status, MW

  • Under contract20%200 MW
  • Right of first refusal80%800 MW
Source: Company statements via Data Center Dynamics
Show as table
PartValueShare
Under contract20020%
Right of first refusal80080%
AI infrastructure demand is not theoretical for us. It's backed by long-term customer commitments, and our focus is on delivering against them.Wes Cummins, chairman and CEO of Applied Digital

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

Harwood rejects data center permit rule for Applied Digital campus

The 75.6% vote leaves the proposed 1GW campus on its existing permitting path with 800MW still uncontracted.

Infrastructure

Applied Digital signs 150MW hyperscaler lease worth $5.4 billion

The 18-year contract lifts contracted base-term revenue above $41 billion, or $100 billion including all renewals.

Infrastructure

Applied Digital signs agreement for access to up to 1GW of potential power capacity in Finland

The developer's first project outside the US is anticipated to have initial power available beginning in 2028, and the company says it has begun marketing the site while in discussions with hyperscale customers.

Infrastructure

Promera buys B&G Energy for data center electrical work

The Irish contractor installs low-, medium- and high-voltage power systems and controls linking generators, UPS and battery storage.

Infrastructure

XTX Markets launches 22.5MW data center in Finland

The quant trader has spent more than €400 million on the Kajaani site and says permitting delays leave power for a third building uncertain.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections

Applied Digital readies first 25MW hall at Polaris Forge 2